Task 10: Run Failback Recovery Plan

Failback Recovery Plan

In this task, you will move the test VM back to the original protected site. This task can be performed either from the protected site’s or the recovery site’s SRM console. The steps are identical in both cases.

Exercise 1: Run Recovery Plan

Step 1: Run Failback Recovery Plan

  1. In either the recovery or protected site’s SRM interface, click Recovery Plans. You may need to re-authenticate to the other site.
  2. Select your Recovery Plan.
  3. Click RUN.

Step 2: Failback Recovery Confirmation Options

  1. Ensure the checkbox is selected for I understand that this process will permanently alter the virtual machines and infrastructure of both the protected and recovery datacenters.
  2. Since you’re performing a planned failback to the original protected site, select Planned migration as the recovery type.
  3. Click NEXT, then click FINISH.

Monitor progress. When the recovery plan run completes, go to the primary site’s vCenter Server and confirm that the test VM is back online and attached to its original network segment.

Now that the test VM is running in the protected site, you need to also restore replication towards the recovery site. This is done by reprotecting the VM again. Repeat the steps you followed in the previous task for Reprotecting a VM.

This completes the lab for VMware SRM Disaster Recovery scenario.


Last modified December 17, 2024: update workflow (8881230)